Covering Saleh Wulu School

Signing of the contract :

Our company, Hamza Abbas Company, concluded a contract with the Education Committee in the city of Manbij with the aim of covering the Salih Lulu School located in the city of Manbij, which is considered one of the most important schools in the city due to its geographical location in the city center, the large area it occupies, and the number of students enrolled in it. The contract duration is 180 days, starting on 8/8/2023. The project was implemented in accordance with the required technical specifications, within the specified time period, and within the limits of the allocated budget .

Evaluation and planning :  

One of our company’s engineers visited the project site, accompanied by a specialized committee from the Education Committee, to hand over the project site to us and determine the work mechanism that must be followed to complete all the work entrusted to our company to implement .

Mechanism of Action :  

We employed an integrated team of engineers with different specializations, logisticians, workers, and technicians, and developed a work plan with a timetable that matches the contractual duration of the project to complete the work on time and with the highest quality .

Among the tasks assigned to our company to carry out are :  

1-Preparing the school building internally:

interior plastering work for the walls and ceilings, painting work for th e walls and ceilings, ceramic work for the walls with a height of 1.5 meters, tiling work for the floors of classrooms and corridors, installing windows and doors, installing wall blackboards for the classrooms, and serving the school building with health and electrical services .

 

2 -Preparing the school building externally:

 We carried out a unique work for the first time in the city of Manbij. The front facade of the school was made of Ecobond, and the side and back facades were made of mankoush paint with thoughtful color coordination to be like a wonderful artistic painting .

 

 

3-Preparing the bathroom block:

 interior plastering work for the walls and ceilings, painting work for the walls and ceilings, ceramic work for the walls at the required height, tiling work for the floors, installing doors and windows, and carrying out sanitary work to the fullest extent, as it is the basic element in the bathrooms to perform their work and serving the block with electrical work .

 4 – Preparing the courtyard and the external fence:

tiles for the courtyard in consistent colors and a group of drawings within the tiles, and building an external wall for the school supported by a group of columns and a chain of reinforced concrete and spraying it with Tyrolean spray, the color of which is consistent with the colors of the courtyard tiles and the colors of the facades of the school building .

 5 – Preparing playgrounds:  

We have equipped a football field and a basketball court with the required sizes and technical conditions, conforming to international specifications for implementing playgrounds.

Evaluation and project delivery :

The project was completed on time and delivered to a specialized receiving committee formed by the Education Committee, from which we received praise for the quality of the work, the speed of implementation, and the organization followed in the work .

 

And here we are today, Hamza Abbas Company, adding a new success to our series of successes by implementing the largest and most important projects in the city. This success is due to cooperation, organization, and working as one team of the company’s management, engineers, technicians, and workers .

Creating Toilets in Informal Areas in Manbij

Tender Announcement:

On July 25, 2023, a humanitarian organization issued a tender with the aim of creating toilets in the informal areas of the city of Manbij.

Our company, Hamza Abbas, reviewed the required work items, conditions, and technical specifications of the materials needed. We then studied the financial offer and developed a necessary timeline for completing the work.

We submitted the tender, complying with the required documents such as company certifications, financial offer, catalogs of the required materials, our previous experience in the same field, and more.

Our company had the highest qualification to execute this project.

Contract Signing:

On September 20, 2023, our company signed a contract to implement the project of creating toilets in the informal areas of Manbij for a contract period of sixty days.

Detailed Explanation of the Implemented Works:

First: Tents Toilets:

1. Implementing regular concrete for the toilet floor according to the required concrete caliber specified in the technical specifications.

2. Preparing the complete structure of the toilet using the metal structure and canvas on two layers, along with all the necessary materials for the structure, such as thread, needle, etc., complying with the technical specifications.

3. Installing PVC doors for the toilets, including all necessary accessories.

4. Installing PVC pipes with the specified diameters in the technical specifications, along with elbows for the drainage process.

5. Excavating a technical trench for each toilet and providing it with a reinforced concrete cover for protection.

6. Installing a toilet bowl that meets the required technical specifications.

Second: Tents Toilets for People with Special Needs:

During the project implementation, we encountered individuals with special needs, so we modified the toilets to accommodate their movement, as follows:

1. Implementing regular concrete for the toilet floor according to the required concrete caliber specified in the technical specifications.

2. Preparing the complete structure of the toilet using the metal structure and canvas on two layers, along with all the necessary materials for the structure, such as thread, needle, etc., complying with the technical specifications.

3. Installing PVC doors for the bathrooms, including all necessary accessories.

4. Installing PVC pipes with the specified diameters in the technical specifications, along with elbows for the drainage process.

5. Excavating a technical trench for each toilet and providing it with a reinforced concrete cover for protection.

6. Installing a special-framed toilet seat for people with special needs.

7. Installing iron handrails to facilitate the movement of individuals with special needs.

8. Implementing a reinforced concrete ramp for people with special needs according to the attached plans.

Third: Toilet Facilities:

1. Installing a sink according to the required technical specifications.

2. Installing a small water tank for each sink.

3. Constructing a metal structure to support the water tank.

4. Implementing river gravel around the facilities according to the required technical conditions.

Impact of Hamza Abbas Company:

 

We, Hamza Abbas Company, take pride in carrying out this type of work as it serves a special segment of society and relieves their burden. Thus, we announce the successful completion of a new project within the contract period and add another success to our achievements.

Manufacturing and Installing Shelter Tents in Raqqa

Contract Signing           

Contract Signing           

 

 

Manufacturing and Installing Shelter Tents in Informal
Settlements in Raqq

 

On January 30, 2024, our company, Hamza Abbas, signed a
contract with a non-governmental organization for the manufacturing and
installation of 123 shelter tents.

 

 Allow me to provide a detailed explanation of the required
tent structure, designed to withstand both vertical and lateral loads:

 

Tent Structure Components

Metal Tent Pegs  

 These pegs are utilized to assist in maintaining the

shape of the tent and securing it in place against strong
winds.

 

Thermal Wool Blanket  

This blanket serves as an effective thermal insulator
for the tent’s surfaces.

 

Canvas Tarpaulin 

 This waterproof material is used to shield the tent’s
surfaces from water.

 

Gutter 

The gutter is installed to prevent water leakage and provide minimal thermal
insulation for both the surfaces and sides of the tent.

 

12mm Thick Rope

 

This sturdy rope is employed to securely fasten the layers of the tent in
their designated positions.

 

Binding Wire 

 The binding wire is used for structural connections and fastening purposes.

 

Tent Manufacturing

We have meticulously manufactured the required tents,                                                                                              
strictly adhering to the                                                                                                                                                    

specified technical specifications.

 

 Tent Installation

These tents have been successfully installed in informal
settlements within a maximum distance of 50 kilometers from the city of Raqqa,
in locations that were carefully coordinated with the supervisory body
established by the organization.

 

Project Completion and Company Pride                                                                                                                                                                                                As Hamza Abbas Company, we take great pride in the
execution of such projects, as they cater to the needs of a specific segment of
society, alleviating their burdens.

 

 

We proudly announce the completion of yet another project,
further augmenting our track record of success.

Drilling and Equipping Wells in Southern Amuda district

Project Background and Tender Process
Due to the severe water shortage in Al-Hasakah city, one of the concerned parties proposed the idea of a marine wells project to provide water for the city.

After conducting geological surveys and determining the drilling depths to reach seawater and ensure its suitability for drinking after treatment, the project idea was adopted, and a tender was launched to select the company to implement the project.

Our company, Hamza Abbas, scored the highest points for implementing this project based on several criteria: financial proposal, type of required excavator, other necessary equipment, and previous experiences.

Contract Signing
On 21/11/2023, the supporting party signed a contract with our company, Hamza Abbas, to drill, equip, and isolate a group of wells in southern Amuda district in order to obtain potable water to irrigate Al-Hasakah city.

I will provide a detailed explanation of the process we followed in the work:

First: Team Preparation
Preparing a team consisting of specialized engineers (civil, survey, laboratory) and experienced workers in the field of drilling wells and assistant workers.

Second: Project Review and Coordination
Our company’s engineering team reviewed the tender documents and technical specifications of the project and visited the drilling site to coordinate with the supervisory body appointed by the supporting party to determine the work procedures to be followed and to develop a timeline for implementing the work.

Third: Commencement of Work
On 18/2/2024, work began, where our company’s survey engineer coordinated with the project’s supporting party engineer to determine the coordinates of the first well.

Steps of well drilling:
1- Cleaning the well site, removing all obstacles, leveling the site with suitable machinery, and giving the site a slope for surface water drainage.
2- Implementing a reinforced concrete pour to protect the wellhead.
3- Commencing drilling operations.
4- Applying protection: Metal casing with a diameter of 18 inches and a thickness of 4 mm of helical type.
5- Applying insulation: Made of rust-free, smooth steel
6- Injecting sulfur-resistant cement grout between the well wall and the insulation using drilling rig compressors.
7- Final lining: Spirally wound and perforated steel plates with artistic patterns on the plunger.
8- Taking geological samples every 10 meters and whenever the layer changes, drying the sample, placing it in transparent nylon bags, numbering them according to their depths, and drawing the lithological column based on the samples taken.

Fourth: Submitting a file for each well containing: 

1-Soil samples.

2-Detailed report on drilling operations (drilling diameter, protection, insulation,          and final lining diameters and thicknesses, well lithological column).

 

3-Detailed report on pumping test results (flow rate, static level, dynamic level,  test depth).

Elevations of Drilled and Perforated Plungers
We, Hamza Abbas Company, are proud to implement this major project for the first time in the region, recognizing its significant service importance to the region’s residents.

In doing so, we have enhanced the experience and capabilities of our company in implementing large-scale service projects.

Construction of a General Clinic in Al-Asaliyah Village, Manbij

Contract Signing
Building a general clinic in the village of Al-Asaliyah in the countryside of Manbij.
On August 15, 2023, our company, Hamza Abbas, signed a contract with the Health Committee in Manbij and its countryside to establish a complete building from foundation to final finishing for use as a general clinic for the village of Al-Asaliyah and nearby villages.

Project Planning and Timeline
One of our specialized engineers reviewed the technical specifications, engineering plans, and financial estimates prepared to execute this project.
They developed a timeline to complete the work entirely, which was set at ninety days.
An agreement was reached between our company and the Health Committee on a contractual period of ninety days to complete the work and deliver the building in its final form.
I will provide a detailed explanation of the sequence of tasks we carried out and how we executed them:

Foundation Work
Our survey engineer surveyed the foundation location, after which we excavated and poured the foundations and laid the shenagat (foundation walls) according to the attached plans.

Reinforced Concrete Works
We started by pouring the columns and then the slab, adhering to the required concrete caliber according to the technical specifications and the reinforcement steel shown in the attached plans.

Finishing Works
After completing the structure, we began the finishing process, including blockwork, internal and external plastering, painting, roughcast, ceramics, and tiling.

Electrical and Plumbing Works
We executed electrical and plumbing installations according to the required technical specifications, using the highest quality materials and the latest techniques and skills.


Sidewalk and Gate Installation
We constructed a perimeter sidewalk around the building using interlock bricks and installed a main gate for the building’s fence.

Final Touches and Completion
Finally, we completed the final touches, cleaned the building from any construction debris, and prepared it fully within the contractual period for official handover to the specialized acceptance committee formed by the Health Committee to ensure compliance with the required technical specifications and the completion of all works.

Project Success Factors
The credit for the accomplishment, success, and timely delivery of this project goes to the skill of our team in the company, including engineers, technicians, and workers, along with the coordination between our team and the supervisory committee appointed by the Health Committee.
 
Today, Hamza Abbas Company proudly announces the completion of another project, adding another success to our track record.

Supply and installation of solar power for the Education Committee in Manbij and ist countryside.

On 16/8/2023, our company, Hamza Abbas, signed a contract with the Education
Committee in the city of Manbij with the aim of supplying and installing solar power for
the Education Committee and ist affiliated institutions for a contractual period of thirty
days.
Allow me to provide a detailed explanation of the procedure we followed:
Firstly, our company’s engineer reviewed the technical specifications and requirements
specified for the materials (panels, batteries, inverters, electrical cables, etc.) for
importation from abroad.
Secondly, upon arrival of the materials, we ensured their technical specifications and
compliance with the technical requirements mentioned in the technical specifications
document attached to the contract.
Thirdly, in coordination between our company’s engineer and the supervisory committee
from the project sponsor/the Education Committee, solar power systems were installed
with skill and professionalism.
Locations where solar power was installed include:
1. The Education and Teaching Committee in the city of Manbij.
2. The General Administration of City Schools / Al-Farat – Abu Qalqal – Al-Karsan.
3. Teachers Training Institute.
4. Language Education Office.
Fourthly, as a result of the diligent work of our skilled workers and adherence to the
supervisor engineer’s instructions and coordination between our company’s engineer
and the supervisory committee affiliated with the Education Committee, the work was
completed within the agreed contractual period and budget allocated for these works.Fifthly, the work was officially handed over to the relevant acceptance committee to
ensure that the executed material specifications comply with the required material
specifications and to ensure the completion of the work in full and to conduct tests on
the power systems to ensure their proper functioning.
Finally, we, at Hamza Abbas Company, take pride in completing this work successfully,
thus succeeding in another field – supplying and installing solar power – in addition to
our other areas of work
Rehabilitation of the Water Tank in Manbij City (Isolation)
Project Overview
• On 18/4/2023, our company contracted with a humanitarian organization to
rehabilitate the water tank in Manbij City for a period of thirty days.
• I will provide a detailed explanation of the work we carried out to complete the
project successfully:
Project Assessment and Planning
• One of our company’s engineers, specialized in this field, accompanied the
supervisory committee from the supporting authority of the project to visit the
project site, assess its current condition, identify the necessary works to make
the tank usable, determine the timeframe needed to complete the works entirely,
and review the technical specifications required to start the works.
Removal of Cracked Parts and Debris Clearing
• The first task we executed was removing the cracked parts from the tank’s
surface, treating the cracks with cement mortar, and clearing the debris.
Application of Waterproofing Layer
• Then we applied a waterproofing layer to the tank’s surface consisting of
bitumen rolls and a primer base coat.
Implementation of Agricultural Soil Layer
• Next, we implemented a layer of agricultural soil to protect the insulation layer
above the tank’s surface.
Repair of Cracks in Tank Walls
• We then addressed the cracks in the tank walls using cement plastering with a
Tyrolean finish.
Installation of Rainwater Drainage Filters
• Subsequently, we installed filters for rainwater drainage.Maintenance of Doors, Windows, and Installation of Protection Grid
• Finally, we carried out maintenance work on the doors and windows of the
toilets and installed a metal protection grid for them.
Completion of Works
• Thanks to the cooperation between our company’s team and the supervisory
committee from the supporting authority, the work was completed with technical
expertise and quality within the specified timeframe.
Handover to Official Acceptance Committee
• It was handed over to the official acceptance committee to ensure the
completion of the works in full accordance with the technical conditions
specified in the contract.
Company’s Pride in Accomplishment
• We, at Hamza Abbas Company, take pride in completing this work, adding
another success to our achievements.
Rehabilitation of Qokhar School in Manbij

Contract Signing

• On January 27, 2024, our company, Hamza Abbas, signed a contract with a humanitarian organization to renovate and maintain Ghuqar School located in the outskirts of Manbij city.

Assessment and Planning

• One of our company’s engineers visited the school site along with a specialized committee from the organization to assess the current condition of the school, identify the necessary rehabilitation and preparation works, determine the budget required to complete these works, and establish the timeframe needed to finish the renovation and maintenance tasks.

• It was agreed upon that a total of 45 days would be allocated to complete the works in full.

Main School Building Maintenance

• The main school building was in good condition and required minor maintenance for the classroom doors and the external door, such as painting and lock replacements, among other things.

Secondary Annex Building Restoration

• However, the secondary annex building of the school needed building restoration and addressing water leakage issues.

• The classroom walls and corridors needed painting, and the doors and windows required maintenance and replacement of any damaged parts.

• Additionally, the installation of boards in the classrooms was required.

• Electrical, water, and sanitation services needed to be provided to the secondary school building.

Restroom Facilities Rehabilitation

• Regarding the restroom facilities, the works included painting, ceramic restoration, roof insulation to prevent leakage, maintenance of doors and windows, sewer cleaning, and providing electrical and water services.

• A special needs bathroom was also constructed.

 

Additional Works for Students‘ Activities

• After completing the essential works, we proceeded to carry out additional works to encourage students in their activities.

• This included the preparation of a football field, a basketball court, and the execution of wall paintings to showcase the school in ist best light.

Completion of Works

• Thanks to the diligent work of our skilled workers and the cooperation between our supervisory committee and the organization’s supervisory committee, the works were completed.

 

 

Repairing Private Homes in Raqqa Province

On March 28, 2023, our company, Hamza Abbas, entered into a contract with a humanitarian organization for the rehabilitation of private homes in Raqqa Province.

These homes are old and, due to the passage of a significant amount of time since their construction, they are in need of maintenance and restoration. To assess the current condition of these homes and determine the necessary work for each one to make it suitable for habitation, an engineer from our company, accompanied by an engineer from the organization, conducted site visits. They carefully evaluated the state of the homes, identified required repairs, and estimated the time and budget needed to carry out the work using high-quality materials.

Allow me to provide a simplified overview of the tasks we undertook and the procedures   we followed when entering each home:

1. Construction and Finishing Works:

– Excavation and demolition: We performed necessary excavation and demolition work, repurposing any salvageable materials for backfilling. If not applicable, we coordinated with the municipality for proper disposal in designated areas.

– Concrete works: We executed various concrete works, including reinforced concrete, ordinary concrete, submerged concrete, and precast concrete, based on the specific requirements. Additionally, we repaired any damaged existing structures.

– Block construction and repairs: We constructed blocks, carried out repairs, and implemented internal and external cement plaster for walls and ceilings. We also addressed cracks, filled gaps with cement mortar, conducted maintenance on chimneys, and ensured proper drainage. Furthermore, we applied an external Tyrolean finish and installed handrails for stairs.

2. Doors and Windows:

– Maintenance and repair: We carefully maintained and repaired doors and windows, which encompassed different materials such as wood, iron, aluminum, and PVC. We also installed necessary accessories. In cases of severe damage, we replaced doors and windows with new ones as required.

3. Tile, Ceramic, and Paint Works:

– Restoration and application: We restored damaged tiles, ceramic surfaces, and paint in all affected areas inside the homes. Additionally, we installed new tiles, ceramic elements, and paint for the newly executed sections.

 

4. Plumbing and Sanitary Works:

– Drainage system maintenance: We ensured proper functionality by clearing sewage drains, repairing damaged components, and optimizing the system’s performance.

– Installation of sanitary fixtures: We installed Arabic toilets, French toilet seats, water taps, basins, water tanks, water pumps, and any other necessary items that serve the residents of the houses.

5. Electrical Works:

– Electrical network maintenance: We meticulously inspected and maintained the electrical network in each home, ensuring its safety and functionality.

– Installation of electrical components: We installed light points, switches, and circuit breakers as required to meet the specific needs of each house.

Thanks to the diligent efforts of our skilled workers and the effective collaboration between our company’s team and the supervisory committee appointed by the organization, the project was successfully completed. We officially handed over the completed work to the designated acceptance committee, ensuring that all agreed-upon tasks were fulfilled in accordance with the technical specifications outlined in the contract. The project was completed within the agreed-upon timeframe and budget allocated for the comprehensive execution of the work.

 

As Hamza Abbas Company, we take pride in adding this achievement to our list of successful endeavors. We are honored to have contributed to the betterment of this segment of society through the delivery of this project.

Construction of Agricultural Guidance Building in Al-Farat Line

On August 28, 2023, our company, Hamza Abbas, entered into a contract with the Agriculture and Irrigation Committee in Manbij to construct a comprehensive building to serve as an agricultural guidance center in the village of Al-Asaliyah for a contract duration of 100 days.

I would like to provide a detailed explanation of the work process we undertook: Firstly, we received the site/land where the project would be implemented from the supporting party, the Agriculture and Irrigation Committee in the city of Manbij.

Secondly, we formed a committee consisting of a civil engineer and specialized technicians, equipping them with the necessary plans and technical specifications to oversee the project and collaborate with the supervisory committee established by the Agriculture and Irrigation Committee. This collaboration aimed to ensure the completion of high-quality work that meets the required standards and employs the latest technology.

Thirdly, we assembled a trained team comprising various professionals, including carpenters, ironworkers, painters, and others. Additionally, we employed a group of assisting workers who were obliged to wear safety equipment such as helmets, gloves, and sturdy boots to prioritize their well-being and safety.

Fourthly, we commenced the construction process, starting from the foundation and progressing through subsequent stages to complete the structural framework. We diligently adhered to the architectural and construction plans, as well as the specified technical requirements. Subsequently, we proceeded to undertake the internal and external finishing of the building, ensuring compliance with the required technical conditions for the materials used. Our aim was to deliver a fully integrated building characterized by meticulous precision, craftsmanship, and the use of top-quality materials.

Finally, we formally handed over the completed project to the designated acceptance committee, which was comprised of experts appointed by the supporting party, the Agriculture and Irrigation Committee in Manbij. We accomplished this within the agreed contract period and in accordance with the predetermined project budget.

The success of our work can be attributed to the fruitful collaboration between the supervisory committee appointed by the supporting party, the Agriculture and Irrigation Committee, and our own supervisory committee. Moreover, the dedication of our work team in diligently following the directives of the supervisory authority, while paying meticulous attention to detail, played a crucial role.

 

Today, Hamza Abbas Company proudly adds another achievement to our portfolio in the field of construction and development.

Aargau Advertising Agency Appenzell Ausserrhoden Advertising Agency Appenzell Innerrhoden Advertising Agency Basel-Landschaft Advertising Agency Basel-Stadt Advertising Agency Bern Advertising Agency Fribourg Advertising Agency Geneva (Cenevre) Advertising Agency Cenevre Advertising Agency Glarus Advertising Agency Graubünden Advertising Agency Jura Advertising Agency Lucerne (Luzern) Advertising Agency Neuchâtel Advertising Agency Nidwalden Advertising Agency Obwalden Advertising Agency Schaffhausen Advertising Agency Schwyz Advertising Agency Solothurn Advertising Agency St. Gallen Advertising Agency Thurgau Advertising Agency Ticino (Tessin) Advertising Agency Uri Advertising Agency Wallis Advertising Agency Vaud Advertising Agency Zug Advertising Agency Zurich (Zürih) Advertising Agency Aargau Werbeagentur Appenzell Ausserrhoden Werbeagentur Appenzell Innerrhoden Werbeagentur Basel-Landschaft Werbeagentur Basel-Stadt Werbeagentur Bern Werbeagentur Fribourg Werbeagentur Genf Werbeagentur Glarus Werbeagentur Graubünden Werbeagentur Jura Werbeagentur Luzern Werbeagentur Neuenburg Werbeagentur Nidwalden Werbeagentur Obwalden Werbeagentur Schaffhausen Werbeagentur Schwyz Werbeagentur Solothurn Werbeagentur St. Gallen Werbeagentur Thurgau Werbeagentur Tessin Werbeagentur Uri Werbeagentur Wallis Werbeagentur Waadt Werbeagentur Zug Werbeagentur Zürich Werbeagentur Switzerland Werbeagentur Schweiz Advertising Agency